Brix Paving Northwest Inc Projects

We are proud to share some of our projects with you so you may understand the wide scope of our capabilities. Check out some of our recent projects on our Visit our Facebook Page Here!

ODOT 99

What we did: We performed a project involving 7.5 inches of full-depth paving on the B lanes, followed by a 2.5-inch top lift on all lanes after milling. In collaboration with ODOT, we conducted a test to determine if a 5.5-inch single lift in a confined area could meet ODOT’s compaction rates and ridability standards. We found that using multiple lifts allowed for proper compaction. The process was successfully completed with a rubber tire roller and an ODOT-approved rolling pattern. This approach likely shortened the project duration by approximately 15 days, allowing all lanes to be reopened to the public sooner.

Supplier: Knife River

Owner: ODOT

General Contractor: K&E

40 Mile Loop: Blue Lake- Sundial and Harlow Road

What we did: Brix Paving Northwest paved bike/walking paths along the 40 Mile Loop on the Sandy River and the Columbia River. Approximately 2,000 tons of asphalt were laid for the 1.7 miles of trail on Sundial Rd. and the 1,900 ft on Harlow Rd.

Supplier: Knife River Sundial

Owner: Oregon Department of Transportation

General Contractor: K & E Excavating, Inc.

ODOT US26: Salmon River – Zigzag Section:

What we did: Brix and subcontractors performed the following work from late July through November 2023 on a section of US26 from Salmon River Drive to Zigzag in Welches, OR. This project includes: paving travel lanes, shoulders and median, constructing ADA ramps, constructing a shared-use path, modify existing traffic signals, replacing existing striping and rumble strips, installing signage, replacing the waterproofing membrane and strip seal expansion joint on the Salmon River bridge, installing, or adjusting guardrail, and performing any other additional work as called for by the specifications and plans.

Supplier: Knife River

Owner: Oregon Department of Transportation

General Contractor: Brix Paving Northwest, Inc.

River Terrace

What we did: Paving for 143 single-family lots, and 2 multi-family lots on a 38-acre site in Tigard.. 250,000+ sq ft of asphalt placed at various depths.

Supplier: Knife River

Owner: Pacific Community Design

General Contractor: earthwork contractor D&T Excavation

Oswego Town Square Parking Lot

What we did: Full parking lot rehabilitation. Cold plane removal with 3.5″ paving, and striping done by Brix.

Supplier: Knife River Coffee Lake

Owner:  Jones Lang Lasalle

General Contractor: Deacon

City of Albany

What we did: Brix Paving Northwest was responsible for Paving Queen Avenue in Albany. Over 3,000 tons of 3/8” AC and 4250 tons of ½” AC.

Supplier: Riverbend

Owner: City of Albany

General Contractor: K & E Excavation, Inc.

Forest Grove Overlays

What we did: Brix Paving Northwest was successful on the 2018 overlay and ramp replacement package. Brix Paving Northwest removed approx. 3,400 feet of an asphalt pathway and replaced it with a new concrete pathway. The project also included replacing 28 ADA ramps and multiple grinds and inlays throughout the city.

Supplier: Lakeside Industries

Owner: City of Forest Grove

General Contractor: Brix Paving Northwest, Inc.

Hagg Lake Perimeter Road

What we did: Brix Paving NW was contracted by Westech Construction to pave a two-way perimeter road around Hagg Lake. Cold in Place recycled was placed in the travel lanes at a width of 24 feet. We then overlaid the entire road 40 feet wide at a depth of 2 inches. We were able to lay down over 2,000 tons for multiple days. The project consisted of over 16,000 tons. We received all possible bonuses on this project.

Supplier: Lakeside Industries

Owner: Federal Highway/ Washington County

General Contractor: Westech Construction

Hagg Lake Federal Paving Project

Project: Rivergate Amazon

What we did:

Paved all parking lots and truck access for Amazon Distribution Center in Portland. Over 21,000 tons of asphalt were placed within 3 months.

General Contractor: Skanska Construction

Asphalt Supplier: Knife River